Ordering speed reductions

When there is a need to reduce the speed on the S-train infrastructure track in connection with projects or maintenance, it requires a speed reduction.

Ordering temporary speed reductions on the S-train

Temporary speed reductions on DSB's infrastructure on the S-train are always ordered from Train Controller S-train (TKC-S). Orders to the Traffic Control Centre S-train (TKC-S) must always be submitted using the form and sent by email to tkc-s@dsb.dk.

Once the order has been processed and approved, it will be returned to the requester.

+ Download form

How to fill in the order form:

The headings below refer to the items on the order form.

Order date: The date on which the order is submitted to tkc-s@dsb.dk.

Requester: The requester fills in the fields with name, company name/place of work, phone number and the email address to which the completed circular is to be sent.

Route: The route can be found in the Route Overview (e.g. 820, 840, etc.).

Validity period: E.g. From 27.08.2019 01:59 To 30.08.2019 08:00.

Area: Specify the track or track area where the condition applies, from km to km. Points no.*

Reason: Tick the reason for the temporary speed reduction.

Comment: Here you can enter any comments that cannot be attributed to the above items.

*(The entire condition must be within the axle counter section belonging to the points)